2013二级建造师市政实务考试大纲解析(一)
2013/2/25 14:41:38 0人评论 453次浏览 来源:学信教育网
为加快施工速度与节约模板加工,柱的施工时间应与水池池壁的施工时间同步进行,柱模板的加工数量 应视总量而定。在能保证总工期的前提下,尽量减少一次投入量。一般柱体分为两次浇筑:第一次浇筑 根部混凝土,第二次浇筑到柱帽顶或梁底。 1.柱的施工程序 柱轴线及边缘放线→施工缝凿毛与清刷→绑扎柱根钢筋(调整)→安装柱根模板→验收→浇筑混凝土→养 护→柱根顶部凿毛→绑扎柱身钢筋→安装柱身(包括柱→帽)模板→绑 扎柱帽钢筋→验收→浇筑混凝土→养护(拆模后继续养护)→柱顶凿毛。 2.柱模板采用钢模或木模(多层胶合板) 柱身混凝土浇筑应一次到顶,浇前施工缝应充分湿润,应铺垫与混凝土配比相同的水泥砂浆。混凝土坍 落度不宜大于80 mm,分层(不超过400 mm)浇筑与振动,为使混凝土沉实,浇到柱帽底部时应暂停后作 二次振动,待全部浇完后,再作二次振动。
当前第 102 页 共 158 页 上一页 [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] [29] [30] [31] [32] [33] [34] [35] [36] [37] [38] [39] [40] [41] [42] [43] [44] [45] [46] [47] [48] [49] [50] [51] [52] [53] [54] [55] [56] [57] [58] [59] [60] [61] [62] [63] [64] [65] [66] [67] [68] [69] [70] [71] [72] [73] [74] [75] [76] [77] [78] [79] [80] [81] [82] [83] [84] [85] [86] [87] [88] [89] [90] [91] [92] [93] [94] [95] [96] [97] [98] [99] [100] [101] 102 [103] [104] [105] [106] [107] [108] [109] [110] [111] [112] [113] [114] [115] [116] [117] [118] [119] [120] [121] [122] [123] [124] [125] [126] [127] [128] [129] [130] [131] [132] [133] [134] [135] [136] [137] [138] [139] [140] [141] [142] [143] [144] [145] [146] [147] [148] [149] [150] [151] [152] [153] [154] [155] [156] [157] [158] 下一页
(责任编辑:·静)
更多 考试快讯 文章推荐
- 2012二级建造师市政实务考试试题及答…(2013-2-16 14:02:17)
- 2011年二级建造师市政实务真题及答案…(2013-2-16 14:02:17)
- 2010二级建造师市政实务真题(2013-2-16 14:02:17)
- 2009二级建造师市政公用真题(2013-2-16 14:02:17)
- 2005二级建造师市政实务考试真题及答…(2013-2-16 14:02:17)
- 2006年二级建造师市政实务真题及答案…(2013-2-16 14:02:17)
- 2012年10月二级建造师市政工程真题(…(2013-2-16 14:02:17)
- 2012年二级建造师:市政公用工程管理…(2013-2-16 14:02:17)
- 2012二级建造师考试:市政公用工程管…(2013-2-16 14:02:17)
- 2012年二级建造师考试:市政公用工程…(2013-2-16 14:02:17)
- 2012年二级建造师:市政公用工程管理…(2013-2-16 14:02:17)
- 2012年二级建造师:市政公用工程管理…(2013-2-16 14:02:17)